Jalmala Boring Works provides permanent and temporary ground anchor systems for diaphragm wall support, retaining walls, deep excavations, basements, and slope stabilization. Our high-capacity anchor piles are drilled, grouted, tested, and stressed to transfer lateral loads into stable ground, ensuring maximum structural stability, minimal wall movement, and safe excavation for commercial, industrial, infrastructure, and metro projects.
Ground Anchor(Tieback) Construction Process
A detailed step-by-step guide of how Jalmala Boring Works installs high-capacity Ground Anchors / Tieback Anchors for deep excavation support.







Survey, Setting Out & Anchor Positioning
Survey, marking, and positioning of anchors with precise inclination and coordinates.
- Survey and mark anchor locations as per approved drawings
- Determine anchor inclination, spacing, depth, and capacity
- Set up Hydraulic Anchor Drilling Rig
- Verify wall levels and drilling coordinates
- Ensure safe working platform and access

Anchor Hole Drilling
Drilling of inclined boreholes using hydraulic anchor rig.
- Drill inclined boreholes through diaphragm wall or retaining structure
- Use Hydraulic Anchor Rig with rotary/percussion system
- Drill to required length and stable strata
- Monitor drilling angle, depth, and diameter
- Clean boreholes using compressed air or water flushing

Anchor Tendon Installation
Insertion of prestressed strands or bars with corrosion protection.
- Insert prestressed steel strands or threaded anchor bars
- Install centralizers, sheathing, and corrosion protection
- Ensure proper free length and bonded length
- Accurate positioning within the borehole
- Pre-grouting inspection and approval

Grouting Operations
High-pressure grouting to bond the anchor tendon with surrounding ground.
- Inject cement grout or chemical from bottom to top
- Create strong bond between tendon and soil/rock
- Fill all voids and ensure complete encapsulation
- Maintain specified grout pressure and quality
- Allow grout to achieve required strength

Anchor Stressing & Lock-Off
Stressing of anchors to design load and lock-off.
- Install anchor heads, bearing plates, and wedges
- Test anchors using hydraulic jacks
- Stress anchors to the required design load
- Lock-off at approved working load
- Record elongation and test results

Quality Control & Excavation Support
Testing, monitoring, and long-term performance verification.
- Verify performance through proof and lift-off tests
- Monitor wall movement and anchor loads
- Install additional levels as excavation progresses
- Complete testing records and documentation
- Provide continuous lateral support to deep excavations
Recent Projects
Specialist Foundation Drilling Contractors
Anchor Pile Drilling in Gujarat
Anchor pile drilling is an important specialised operation in foundation engineering and selected ground-support applications. It involves creating boreholes at specified locations, depths and inclinations according to the requirements of the structural and geotechnical design. Proper drilling execution is essential for achieving the required dimensions and preparing the ground for subsequent installation activities.
These drilling operations may be required in retaining wall construction, basement developments, deep excavation projects and other civil engineering applications where an engineered anchoring or foundation arrangement is specified. The drilling method depends on soil conditions, rock profile, groundwater, site accessibility and project specifications.
Jalmala Boring Works is a third-generation family-owned foundation company established in 1962. With more than 60 years of industry experience, the company undertakes specialised foundation-related operations and drilling work. Based in Ahmedabad, Gujarat, Jalmala Boring Works has experience in projects across more than 20 Indian states.
For construction companies, infrastructure developers and contractors looking for anchor pile drilling services in Gujarat, selecting suitable equipment and following project-specific drilling requirements are important for successful execution.
Understanding Anchor Pile Drilling
Anchor pile drilling involves the use of specialised drilling equipment to create boreholes in soil or rock for an engineered anchoring or foundation system. The drilling location, bore diameter, depth and inclination are determined according to the project drawings and geotechnical requirements.
Depending on the project, drilling may be undertaken for ground anchors, retaining structures or other specified foundation arrangements. The drilling operation must be coordinated with the structural design and construction sequence to maintain the required positioning and dimensions.
Factors such as soil strata, rock formations, groundwater levels, nearby structures and available working space influence the selection of drilling equipment and execution methodology. A site-specific assessment helps determine the appropriate approach for each project.
Drilling Methods for Anchor Pile Projects
The drilling technique is selected according to the ground profile, required bore dimensions, project access and technical specifications. Common drilling approaches may include:
Rotary Drilling
A rotary drilling arrangement uses rotating tools to penetrate soil or rock and create boreholes according to the specified project dimensions.
Hydraulic Drilling
Hydraulic drilling equipment provides controlled drilling operations and may be selected for suitable foundation and anchoring applications.
Rock Drilling
Specialised drilling tools and methods may be required where boreholes pass through hard strata or rock formations.
Cased Bore Drilling
Temporary casing may be used where ground conditions require borehole support during drilling operations.
Anchor Pile Drilling Process
Proper planning and systematic execution are important for anchor pile drilling. The work sequence is generally coordinated with the project drawings, site conditions and construction schedule.
1. Project Assessment and Planning
The project drawings, site conditions, drilling locations, required bore dimensions and ground investigation reports are reviewed before starting the work.
2. Site Preparation and Setting Out
The work area is prepared, access for drilling equipment is arranged and drilling points are marked according to the approved layout.
3. Equipment Positioning
Suitable drilling equipment is positioned and aligned to achieve the specified drilling location and inclination.
4. Borehole Drilling
Drilling is carried out using the selected method and tools based on the soil or rock conditions and required borehole dimensions.
5. Borehole Inspection
The completed borehole is checked for the required depth, alignment and other project-specific acceptance requirements.
6. Further Installation Activities
Depending on the designed system, subsequent work may include installation of anchor tendons, reinforcement or other specified components, followed by grouting where required.
Applications of Anchor Pile Drilling
Anchor-related drilling operations may be required across different construction and infrastructure projects. The final application depends on the structural design and site-specific engineering requirements.
Basement Construction
Drilling operations for suitable anchoring and ground-support arrangements in underground and multi-level basement projects.
Retaining Wall Projects
Anchor drilling for engineered retaining structures where additional ground support is specified.
Deep Excavation
Drilling work associated with selected excavation support systems for deep construction projects.
Diaphragm Wall Projects
Drilling operations for specified ground anchor arrangements connected with diaphragm wall construction.
Infrastructure Development
Foundation and ground-support drilling for suitable civil engineering and infrastructure developments.
Industrial Construction
Specialised drilling requirements for selected industrial facilities and underground construction works.
Important Factors in Anchor Pile Drilling
Drilling quality depends on the coordination of equipment, ground conditions and project specifications. Important factors include:
Soil and Rock Conditions
Different soil strata and rock formations can affect drilling speed, tool selection, borehole stability and execution methodology.
Borehole Diameter and Depth
The drilling dimensions must follow the approved design and project requirements.
Drilling Alignment
Correct positioning and inclination are important for achieving the required anchor or foundation layout.
Groundwater Conditions
Groundwater levels and seepage may influence borehole stability and the drilling procedure.
Equipment and Site Access
The available working area, access restrictions and ground conditions influence equipment selection and positioning.
Quality and Safety
Site supervision, drilling records, equipment checks and appropriate safety practices support controlled project execution.
Anchor Pile Drilling Contractor in Ahmedabad and Gujarat
Gujarat has a wide range of construction, industrial and infrastructure developments that require specialised foundation and drilling services. Anchor pile drilling may be required for selected basement projects, retaining structures, deep excavations and other engineering applications.
Jalmala Boring Works operates from Sarkhej, Ahmedabad, and undertakes foundation-related work across Gujarat and other parts of India. The company has experience in piling, diaphragm wall construction and specialised foundation operations, supported by modern SANY hydraulic equipment.
Project requirements from Ahmedabad, Gandhinagar, Surat, Vadodara, Rajkot, Bharuch, Vapi, Anand, Mehsana and other locations in Gujarat can be discussed with the company. Equipment selection and execution methodology depend on site conditions and project specifications.
For related foundation requirements, you can also explore our anchor pile and ground anchoring services and ground anchor installation in Gujarat.
Why Choose Jalmala Boring Works?
Foundation drilling requires experienced operators, suitable machinery, proper planning and coordination with the construction team. Jalmala Boring Works brings experience developed through three generations of family involvement in the foundation industry since 1962.
60+ Years of Experience
A third-generation family business with a long-standing presence in foundation engineering.
Modern SANY Equipment
Hydraulic piling and diaphragm wall equipment for specialised foundation operations.
ISO 9001:2015
Quality management practices supporting foundation project execution.
Pan-India Experience
Experience in foundation-related projects across more than 20 Indian states.
Specialised Foundation Work
Experience in pile foundations, diaphragm walls and ground anchoring applications.
Project-Focused Execution
Attention to site conditions, equipment planning, safety and project requirements.
Frequently Asked Questions About Anchor Pile Drilling
1. What is anchor pile drilling?
Anchor pile drilling refers to specialised drilling operations carried out to create boreholes for anchor-related foundation or ground-support systems. The drilling method, diameter, depth and arrangement depend on the approved project design and ground conditions.
2. Where is anchor pile drilling used?
Depending on the engineering design, anchor-related drilling may be required for retaining structures, basement construction, deep excavation support and selected infrastructure or foundation projects.
3. Which equipment is used for anchor pile drilling?
The equipment depends on the required bore diameter, drilling depth, soil or rock conditions, site access and project specifications. Suitable hydraulic drilling or piling equipment is selected according to the work requirements.
4. How is the anchor pile drilling process carried out?
The general process includes reviewing the project drawings, assessing ground conditions, setting out drilling locations, carrying out drilling to the specified dimensions and maintaining records for quality control. Further installation, reinforcement or grouting activities depend on the designed system.
5. Can anchor pile drilling be carried out for basement projects?
Anchor-related drilling may form part of suitable basement and deep excavation projects where the approved structural and geotechnical design requires ground support or anchoring arrangements.
6. Does Jalmala Boring Works provide drilling services across Gujarat?
Jalmala Boring Works is based in Ahmedabad and has experience in foundation-related projects across more than 20 Indian states. Contact the company to discuss your project location and technical requirements.
Contact Jalmala Boring Works for Anchor Pile Drilling
Looking for an anchor pile drilling contractor in Ahmedabad or Gujarat? Contact Jalmala Boring Works to discuss your project drawings, drilling requirements, site conditions and construction schedule.
Contact Person: Mr. Amrulla Memon
Phone: +91 93745 45415
Email: jalmala.pile@gmail.com
Location: Sarkhej-Okaf, Ahmedabad, Gujarat 382210, India